Construction Project Updates

8/14/2019

****UPDATED/ONGOING****
LINCOLN WAY STREETSCAPE-
click here for graphic
CONTRACTOR: Central Allied Enterprises, Inc.
ROAD CLOSED: Lincoln Way E (SR172) between ERIE ST and 1ST ST SE to vehicular traffic (July 18th for 90 Days).
Pedestrian traffic to local businesses will be OPEN.
Free Parking (lots and side street parking) available. See Downtown Detour and Parking Map for locations

Detour and Roadway signage is installed and being monitored for adjustments.

South Bound SR241 Detour.
Use 3rd St SE to Tremont Ave SE to Erie Street.

The Engineering Department is actively monitoring the DETOUR and will be making adjustments as necessary to minimize traffic issues. Please report any concerns you may have to Engineering at 330-830-1722 and we will look into it immediately. Thank you for your patience.

We want to keep the community updated on streetscape and what is coming up in the project.
What has been accomplished so far with the streetscape project?
Central Allied Enterprises, Inc; Contractor
CLOSED the road and installed detour signage. The City is monitoring and making adjustments as necessary.
Drainage structures have been installed.
Removed and graded the intersection of Erie Street, 1st St NE, and the mid-block crossing.
Most sidewalk has been removed from 1st St SE to 1st St SW.
Excavated and filled basement voids under various sidewalks.
Rough graded existing sidewalk areas.
Installed electrical conduits for traffic and lighting.
Disconnected traffic signals. (First Energy)
Existing traffic signals removed.
Began forming and pouring curb at 1st St SE intersection.

What is expected to happen next week?
Continue installing electrical and lighting conduits throughout the project limits.
Begin installing base concrete at 1st St SE intersection, prep intersection for paver installers.
Remove existing light poles. (awaiting First Energy).

Any other comments or information Massillon residents should be aware of?
The City has hired JMT, Inc. as their Construction Inspector and Administrator.
There is an inspector on site, continually working in conjunction with the City, the Contractors, and Business owners.
We are monitoring traffic patterns and signal timing of the traffic signals in the area, making adjustments as needed
Any questions or concerns from the public or business owners can be addressed by contacting Engineering at 330-830-1722.

RICHVILLE DR SE IMPROVEMENT PROJECT
CONTRACTOR: Northstar Asphalt, N. Canton, Ohio
Pavement markings to be completed. School Zone signage to be installed

2019 STREET RESURFACING PROJECT and TARGET AREA STREET RESURFACING
CONTRACTOR: Superior Paving and Materials, N. Canton, Ohio
Contractor working on catch basins and curb ramps this week.
We expect Contractor to begin milling and resurfacing beginning week of August 12th.

2019 CATCH BASIN REPLACEMENT PROJECT I
Replacing various Catch Basins throughout the City.
CONTRACTOR: Pryor Property Services, LLC

2019 OPWC 27TH ST/JACKSON AVE RESURFACING PROJECT
CONTRACTOR: Superior Paving and Materials, N. Canton, Ohio

UPCOMING CONSTRUCTION PROJECTS:

2019 CATCH BASIN REPLACEMENT PROJECT II
Award Expected August 20, 2019

SPRINGHILL SETTEMENT UNDERDRAINS PHASE II
Award expected August 20, 2019

ST ANDREWS ESTATES- AUGUSTA DR SE UNDERDRAINS PHASE I
Award expected August 20, 2019

2019 MUNICIPAL ROAD- ERIE STREET SOUTH RESURFACING
SR 21 to Oakwood Cemetary
Bid Opening July 25, 2019. One bid received, over 10% of Engineers Estimate
Determining course of Action