LINCOLN WAY STREETSCAPE-
click here for graphic
CONTRACTOR: Central Allied Enterprises, Inc.
Road Open: Lincoln Way E (SR172) between ERIE ST and 1ST ST SE to vehicular traffic. However, Erie St & 1st St SE remained closed at Lincoln Way.
Pedestrian traffic to local businesses OPEN.
Parking on Lincoln Way is available. See Downtown Detour and Parking Map for additional parking locations.

South Bound SR241 Detour.
Use 3rd St SE to Tremont Ave SE to Erie Street.

Please report any concerns you may have to Engineering at 330-830-1722 and we will look into it immediately. Thank you for your patience.

We want to keep the community updated on streetscape and what is coming up in the project.
What has been accomplished so far with the streetscape project?
Central Allied Enterprises, Inc; Contractor
CLOSED the road and installed detour signage. The City is monitoring and making adjustments as necessary.
Drainage structures have been installed.
Removed and graded the intersection of Erie Street, 1st St NE, and the mid-block crossing.
Sidewalk has been removed from 1st St SE to 1st St SW.
Excavated and filled basement voids under various sidewalks.
Rough graded existing sidewalk areas.
Installed electrical conduits for traffic and lighting.
Installed pull boxes.
Disconnected and removed traffic signals and lighting.
Formed and poured curb curb at 1st St SE intersection.
Removed concrete/steel beams at 1st St SE SW corner.
Underdrains installed.
Installed light pole foundations
Asphalt layer for brick pavers at 1st St intersection
Installed brick pavers in crosswalks at 1st St intersection.
Installed traffic signal foundations
Adjusted catch basins to grade.
Completed grading for new sidewalks and curbs.
Completed 1st St NE intersection pavers.
Completed electrical conduit to mid block crossing.
Replaced broken collapsed 24″ storm sewer.
Finished brick work at mid block crossing.

What is expected to happen this week?
Light poles and traffic light installation expected to begin mid December.

Any other comments or information Massillon residents should be aware of?
The City has hired JMT, Inc. as their Construction Inspector and Administrator.
There is an inspector on site, continually working in conjunction with the City, the Contractors, and Business owners.
We are monitoring traffic patterns and signal timing of the traffic signals in the area, making adjustments as needed
Any questions or concerns from the public or business owners can be addressed by contacting Engineering at 330-830-1722.

RICHVILLE DR SE IMPROVEMENT PROJECT
CONTRACTOR: Northstar Asphalt, N. Canton, Ohio
Pavement markings completed. School Zone signage has been installed.

2019 STREET RESURFACING PROJECT and TARGET AREA STREET RESURFACING
CONTRACTOR: Superior Paving and Materials, N. Canton, Ohio
Project is complete.

2019 CATCH BASIN REPLACEMENT PROJECT I
Replacing various Catch Basins throughout the City.
Project is complete.
CONTRACTOR: Pryor Property Services, LLC

2019 OPWC 27th ST/JACKSON AVE RESURFACING PROJECT
Project is complete.
CONTRACTOR: Superior Paving and Materials, N. Canton, Ohio

2019 CATCH BASIN REPLACEMENT PROJECT II
Replacing various Catch Basins throughout the City. Project nearly complete.
CONTRACTOR: Holderbaum Sewer and Drain

SPRINGHILL SETTLEMENT UNDERDRAINS PHASE II
Installing underdrains at the back of curb. Project began 12/2/19.
CONTRACTOR: Albatross Management

AUGUSTA DR SE UNDERDRAIN PROJECT PHASE I
Installing underdrains at the back of curb. In progress.
CONTRACTOR: Pryor Property Services, began in October.

UPCOMING CONSTRUCTION PROJECTS:

2019 MUNICIPAL ROAD- ERIE STREET SOUTH RESURFACING
SR 21 to Oakwood Cemetary
To be re-bid in January.