Construction Project Updates

04/15/2019

LINCOLN WAY STREETSCAPE
CONTRACTOR: Streetscape project bids to be opened May 2. Anticipated closure of Lincoln Way E between Erie St and 1st St SE to vehicular traffic, (June, July, August). Pedestrian traffic to local businesses will be open.

UTILITIES:
April 15th: Dominion Energy installing new medium pressure 8″ line on south side of Lincoln Way beginning at 1st St SW and continuing east to 3rd St SE. Lane closures are expected.
April 22nd: Aqua Ohio
will be installing new 12″ water main on north side to replace existing 100+yr old water main beginning at 1st St NW. Lane closures are expected.

RICHVILLE DR SE IMPROVEMENT PROJECT
The Roadway is CLOSED to THRU TRAFFIC- LOCAL TRAFFIC ONLY.

CONTRACTOR: Excavating for new curb/gutter and pavement from Southway Ave SE to Jackson Ave SE. Stringing and Pouring new curb/gutter. Replacing Driveway approaches. Landscaping and Seeding. Preparing the roadway at Jackson Ave for new curb/gutter and intersection improvement.

UTILITIES: Dominion Energy is installing 16″ gas pipe line near Southway and Richville Intersection over to Jackson Ave.

LINCOLN WAY WEST BROOKFIELD CREEK BOX CULVERT (ODOT project)
CONTRACTOR: Contract awarded by ODOT and will be inspected by ODOT

UTILITIES:
April 15: Dominion Energy
will be installing 6″ gas pipe line as part of ODOT‘s box culvert replacement project. Expected lane closures during this time.
June 3rd to August 1st: During ODOT‘s Box culvert replacement project, there will be a complete road closure between 29th St NW and 32nd St NW. Detour route will be posted by ODOT.

2019 STREET RESURFACING PROJECT and TARGET AREA STREET RESURFACING
CONTRACTOR: Contract awarded 4/16/2019. Contractor to begin with catch basins and curb ramps week of April 29th.

UPCOMING CONSTRUCTION PROJECTS:

SR21 COXEY PEDESTRIAN BRIDGE REPLACEMENT
Replace pedestrian/bike bridge over State Route 21- expected mid-May 2019

2019 CATCH BASIN REPLACEMENT PROJECT
June 2019

SPRINGHILL SETTEMENT UNDERDRAINS PHASE II
July 2019

ST ANDREWS ESTATES- AUGUSTA DR SE UNDERDRAINS PHASE I
July 2019

2019 MUNICIPAL ROAD- ERIE STREET SOUTH STREET RESURFACING
SR 21 to Oakwood Cemetary
August 2019

2019 OPWC 27TH ST/JACKSON AVE RESURFACING PROJECT
Hankins Rd NE to Harsh Ave SE
August 2019